Listing of articles from ‘Rec Center’


Rec Center - November 13

Thursday November 13th, 2008 in Current, Rec Center | 4 Comments »


Weight room exterior.

Front entrance of Recreation Center.

Weight room and elevated walking track.


Multipurpose rooms.

Indoor gymnasium. Maple wood flooring to be installed.

View of gymnasium from elevated walking track.

View of gymnasium from indoor walking track.

Outdoor splash pool and view of exterior weight room.


Outdoor splash pool with spray features.

Splash pool with spray features.

Shower area with individual shower stalls.

Shallow end of indoor pool.

Indoor pool.


Rec Center Update - Sept 16

Tuesday September 16th, 2008 in Current, Rec Center | 10 Comments »

Front Entrance of the Recreation Center. 


Weight room exterior (red brick).

Exterior of multipurpose rooms.

Second floor group fitness classrooms.

Elevated walking track and view into gymnasium.

Main entrance.


Rec Center Update - 8/20

Wednesday August 20th, 2008 in Rec Center | 2 Comments »

Exterior of the Natatorium South Facade

Exterior of the Natatorium South Facade

img_1419.jpg

Interior of the Natatorium, Looking North & East

Interior of the Natatorium, Looking South

Interior of the Natatorium, Looking South

Exterior Facade of the Workout Area

Exterior Facade of the Workout Area

Interior of the Track over the new Gym

Interior of the Track over the new Gym

Interior of the radius portion of the track over the New Work-out Area

Interior of the radius portion of the track over the New Work-out Area

View over the Exterior Pool with new Coping

View over the Exterior Pool with new Coping

East Elevation of the Multi-use rooms and back of building

East Elevation of the Multi-use rooms and back of building


Rec Center Update - 6/24

Tuesday June 24th, 2008 in Rec Center | No Comments »

r1.jpg

Gymnasium and Natatorium

r2.jpg

Indoor Pool

r3.jpg

Indoor Pool

r4.jpg

Fitness Room and Multi-Purpose Activity Rooms

r5.jpg

Gymnasium

r6.jpg

Indoor Pool, Splash Pad, Fitness Room


Recreation Center Expansion Photos :: May 20, 2008

Friday May 30th, 2008 in Rec Center | 1 Comment »

Facing west - Natatorium (indoor pool)

Facing West - Natatorium (indoor pool)

Indoor pool

Indoor Pool

Preparation work for concrete to be poured for the outdoor splash pool

Preparation Work for concrete to be poured for the outdoor splash pool

Facing south, multipurpose room (black sealant) indoor weight room, natatorium

Facing South, multipurpose room (black sealent) indoor weight room, natatorium

Facing south, multipurpose room (black sealant) indoor weight room, natatorium

Facing south, multipurpose room (black sealant) indoor weight room, natatorium

Indoor gymnasium

Indoor Gymnasium

New sidewalk in front of Recreation Center, parallel to Austin Ave.

New sidewalk in front of Recreation Center, parallel to Austin Ave.

Indoor gym, facing northeast

Indoor Gym, facing northeast

Facing north, gymnasium and main entrance

Facing north, gymnasium and main entrance

Locker rooms and indoor pool

Locker rooms and indoor pool

Facing northwest, indoor pool, weight room

Facing northwest, indoor pool, weight room


Rec Center Update - May 14, 2008

Wednesday May 14th, 2008 in Rec Center | No Comments »
  • We currently have structural steel erected on most of the facility. The remaining natatorium steel is being erected this week and will continue through next week.
  • The masons are installing CMU block for interior and exterior walls at the workout area, main hallways and locker rooms. CMU installation will continue on the new gym late next week and around the natatorium steel after it is erected.
  • Sidewalks, curb and gutter are being formed and poured over the next several weeks. This includes the parking lot next to the football stadium. When the structural steel has been removed from the parking lot area, a second course of base will be placed and then the paving of the lot will take place sometime in early June.
  • The exterior pool shell will be poured early the week of May 19. Plastering for the interior and exterior pools will take the week of June 2.
  • We expect to have the building dried-in by mid-June after which visual progress will be more difficult to observe.
  • Construction completion for the 47,000 square foot addition, including the pools is scheduled for late November. Renovation of the existing 18,000 square foot building is scheduled for completion in late February 2009.

April 8, 2008April 8, 2008April 8, 2008